+971 55 954 5801

About this project

Al Ain has been building and rebuilding parks steadily, and the irrigation pumping behind them is released to site in packages rather than all at once. Almafor has been supplying the pump station automation across several of those packages, at Al Qua'a, Al Khabeesi and the Al Jahili, Al Mitrid and Muwaiji group, with further parks at Al Madif, Al Maqam, Al Moraiji and Fela Hala following as their information is confirmed.

This is a rolling programme rather than a single contract, and some stations are complete while others are still in engineering. Al Qua'a and Al Khabeesi were the first through, with panels delivered and instrumentation installed.

Each station takes an MCC with variable frequency drives for the irrigation pumps and a separate PLC and RTU panel with a local touch screen HMI. Several parks also have water features, which are quoted and built as their own control package because they run on a different schedule from irrigation and there is no benefit in coupling them.

Enclosure choice is one of the few decisions that genuinely varies station to station. Where the panel sits inside a pump room it is sheet steel. Where it stands outdoors it is GRP, because in Al Ain an outdoor steel enclosure is a corrosion and heat problem rather than a cost saving. On this programme that split ran to six sheet steel panels and three GRP.

Material submittals go through the consultant against the municipal circular listing approved manufacturers and suppliers, which constrains component selection before any design work starts. Working to that list from the first submittal rather than arguing for an alternative later is what keeps approval from becoming the critical path.

Because the parks are released one at a time, the panels are built to a common design and then adjusted per station. That keeps the approved submittal reusable, keeps spares interchangeable across the parks, and means each new station is a short repeat rather than a fresh design.

Scope of work

  • MCC panels with variable frequency drives for the irrigation pump sets, in sheet steel enclosures indoors and GRP enclosures for outdoor positions
  • PLC and RTU panels with local HMI, reporting to the municipal irrigation SCADA
  • Separate control packages for the park water features
  • Field instrumentation, instrument cabling and termination
  • Material submittals and consultant approvals to the municipal approved manufacturer list
  • Delivery, installation, testing and commissioning station by station as each park is released

Equipment installed

  • Schneider Modicon M340 processor with discrete and analogue I/O in the PLC and RTU panel
  • Variable frequency drives on the irrigation pump sets
  • Touch screen HMI at each station
  • RTU with GSM communications to the municipal irrigation SCADA over DNP3
  • Sheet steel MCC enclosures indoors and GRP enclosures for outdoor positions
  • Flow metering, level and pressure instrumentation at the pump station

The platforms and controllers we work on

Motor control centre for an Al Ain park irrigation pump station, front view with control and indication
Inside the Al Ain park MCC panel, showing drive, protection and control wiring
PLC and RTU panel with touch screen HMI for an Al Ain park pump station
Flow meters and pipework instrumentation prepared for an Al Ain park pump station

Planning similar work?

Talk to the engineers who delivered this project.

Speak to an engineer See all projects

Trusted By

Abu Dhabi City Municipality
Abu Dhabi Ports
Bilfinger
Schneider Electric
Caterpillar
Hitachi Energy
PcVue Solutions
General Electric
TAQA Transmission
TAQA Distribution
Etihad Water and Electricity
Etihad Rail
Abu Dhabi Investment Council
Schlumberger