+971 55 954 5801

About this project

TRANSCO project N-15223 replaced the substation control and monitoring system across six grid stations, delivered by Almafor as main contractor. The systems being retired were of Alstom and GE manufacture and had passed the point where they could be supported.

The six stations span the full range of the transmission network: a 400 kV to 220 kV station, a 400 kV station, a 220 kV to 33 kV station, and three stations at 132 kV to 11 kV. Each one is a separate cutover with its own outage constraints, which is why the programme ran over several years rather than as a single installation.

Each station received SCMS servers, human machine interface and engineering workstations, IEC 101 gateways, bay control units, fibre optic cabling and a station UPS rated 5 or 6 kVA. The operator and engineering positions were kept on separate machines, because the position that runs a live network and the position that changes its configuration should not be the same keyboard.

Integration reached beyond each station. The systems were connected to the Load Dispatch Centre, the Emergency Control Centre and the Distribution Management System, so that a station is not only locally automated but visible and controllable from the places that actually dispatch the network.

None of this happened on dead plant. Transmission service was maintained throughout, station by station and bay by bay, with each new controller proven against the existing interlocking before anything was transferred to it. The trigger for the whole programme was not failure. It was unsupportability: the platforms still worked, and the spares, the software and the people who understood them had gone.

Scope of work

  • Supply, Installation, Adaptation works, Testing & Commissioning of SCMS servers (CCA), HMI workstations, EWS workstations, Gateways( IEC-101), BCU’s, Printer, New 5/6 kVA UPS
  • Supply of FO cables, interfacing system for protection, BCU, AVR etc.
  • LDC/ECC/DMS integration
  • Schneider Electric EcoFIT System based solution

Equipment installed

  • Schneider Electric EcoFIT based SCMS
  • SCMS servers, HMI workstations and engineering workstations
  • Station gateways on IEC 60870-5-101, and bay control units
  • New 5/6 kVA UPS on each station
  • Fibre optic cable, with interfacing to the existing protection, BCU and AVR
  • LDC, ECC and DMS integration

The platforms and controllers we work on

img 20200712 114536 cbe36fe5
img 3206 d03a6d16
p1160602 855b8cf6
img 3285 f2106cb2
img 5704 692d0bae
img 3409 0a875c76
photo 2 6317ae26

Planning similar work?

Talk to the engineers who delivered this project.

Speak to an engineer See all projects

Trusted By

Abu Dhabi City Municipality
Abu Dhabi Ports
Bilfinger
Schneider Electric
Caterpillar
Hitachi Energy
PcVue Solutions
General Electric
TAQA Transmission
TAQA Distribution
Etihad Water and Electricity
Etihad Rail
Abu Dhabi Investment Council
Schlumberger
ADNEC