Guide
The line in the tender usually reads supply, installation, testing and commissioning. The suppliers worth shortlisting are the ones who can sign for all four words.
Definition
In UAE procurement the words SCADA supplier cover everything from a software reseller who ships licences in an envelope to a contractor who delivers a working system. The difference matters, because a SCADA system is not one product. It is servers and operator screens, the software that runs on them, the control and RTU panels below them, the instruments feeding those panels, and the network tying all of it together. Someone has to supply every one of those items, and someone has to make them behave as one system.
This is why the bill of quantities on most UAE projects does not say supply at all. It says supply, installation, testing and commissioning, and it prices them as one line. The client is not buying boxes. They are buying a screen an operator can trust, and the four words exist because a delivery note proves none of that.
Supply and installation is the core of what Almafor does. We price the whole line: the equipment procured against the asset owner's approved vendor list, the control and RTU panels designed and built in our own workshop in Mussafah Industrial Area, and the installation, termination, testing and commissioning done by the same team that built them. We have delivered on that basis in Abu Dhabi since 2008, and we also integrate what we supply with the control centres and systems already in service.
The practical advantage of buying it this way is simple. When one party supplies the equipment and another installs it, every fault found at commissioning starts an argument about whose it is. When the supplier and the installer are the same company, there is no interface to argue over and no warranty gap to fall into.
Buying models
We deliver the equipment configured and factory tested, and your own team installs it. This works when the buyer has a strong site organisation. The risk sits at the interfaces, which is why we insist on a witnessed factory acceptance test before anything ships, so what leaves the workshop is proven rather than presumed.
One party owns the job from procurement through delivery, installation and termination. This is where most of our contracts sit, and it is the arrangement we would recommend to anyone building or upgrading a station, because the party who selected the equipment is the party standing in front of it on site.
The full line as utilities and municipalities tender it: everything above, plus point to point testing, commissioning and a signed site acceptance certificate. The contract is finished when the operator trusts the screen, and that is the standard we are usually working to.
Bill of material
Track record
On each of these contracts the equipment, the panels and the commissioning came from one company. Follow any card for the scope and the client.
Bawabat Al Sharq Development
Abu Dhabi Municipality
ABU DHABI INVESMENT COUNCIL
Ministry of Energy & Infrastructure
Platforms
The platform is chosen by what your control centre already speaks and what your asset owner has approved, not by what we would rather sell. Most of our recent supply has been Schneider Electric hardware with PcVue or Schneider SCADA above it, and we deliver on GE Vernova and Hitachi Energy systems as well.
Method
The BOM is derived from the signal list and the single line diagram, not copied from a previous job. Every item on it can be traced to a point the operator will see or a load the station will run.
Long lead items, servers, switchgear and communications equipment, are ordered first and tracked weekly. On brownfield work the delivery programme is built around the outages the operator will actually release, because equipment waiting in a store earns nobody anything.
Control and RTU panels are built and wired in our Mussafah workshop while the application and controller logic are configured alongside them, so the hardware and the software meet before site, not on it.
The panels and the application are tested together against the approved schedule, with your engineers present. On the Bawabat Al Sharq pumping station the MCC, the capacitor bank and the PLC system each had their own witnessed test.
The same team that built the panels installs and terminates them. On one potable water pipeline that included supplying and laying seventeen kilometres of fibre optic cable before the SCADA had anything to run on.
Point to point checks from the field device to the screen, commissioning against the operating philosophy, site acceptance testing, then training, as built drawings and the defect liability period.
Common questions
A complete SCADA supply covers the servers and operator workstations, the software licences, the control and RTU panels, the PLCs and I/O inside them, the field instruments, the communications network and the power supplies that keep it all running. In UAE tenders the scope is usually written as supply, installation, testing and commissioning, which means the supplier is also responsible for installing the equipment and proving it works. A supplier quoting hardware alone is answering a different question.
Yes, and that is the point of how we work. The engineers who specify and procure the equipment build the panels in our Mussafah workshop, then install, terminate and commission them on site. Supply and installation as one contract is the core of our business, with integration into existing control centres alongside it. One party owns the result, so a fault found at commissioning gets fixed instead of disputed.
Yes. We supply panels and configured systems for other contractors and in house teams to install, and we have no objection to that arrangement. We ask for a witnessed factory acceptance test before dispatch, because once equipment leaves the workshop the installation quality is outside our control, and the test record is what protects both sides.
Most of our recent supply is Schneider Electric hardware, Modicon controllers and Altivar drives among it, with PcVue or Schneider SCADA above it. We are recognised by Schneider Electric and we also deliver on GE Vernova Proficy and Hitachi Energy MicroSCADA platforms. The honest answer on any specific project is that the brand is set by your asset owner's approved vendor list and what your control centre already runs, and we quote within that.
Yes. The handover package includes a recommended spares list priced per item, and we supply software licence renewals and expansion licences for the systems we deliver. Our advice is to hold the spares that stop the plant, controller CPUs, power supplies and communication modules, and to buy the rest on lead time rather than tying up money in a store.
Panels we build ourselves are governed by our workshop programme and typically run some weeks from approved drawings to factory test. The long lead items are what set the schedule: servers, switchgear and some communications equipment can run to several months in the current market. This is why we order long lead equipment first and build the delivery programme around the outages the operator can actually release.
It depends on the station count, the tag count, the panel scope and the approvals required, which is why we quote against a points schedule and a single line diagram rather than publish a price list. Our guide to automation project costs explains what drives the number honestly, and a one line enquiry with the drawings attached gets a faster answer than most people expect.